Version 4.9 includes the option to have more than two teams reporting on the same activity, e.g. trade, quality and client teams.


  • Setup your activities in the Process Template in a way that more than two teams are allowed to report on the attached QA checklist.
  • This functionality can e.g. be used to include the client on Sablono: Trade would report progress on the activity and upload their QA checklist. Afterwards the main contractors quality team would check the quality and upload their set of answers. Once they approved the client team can check the activity, upload their set of answers and confirm / reject it.
  • Team filters on the web now also include Inspection Team(s).
  • Lot’s of minor improvements and bug-fixes.